Wunstorf, civil engineering works car park

WHAT WAS DONE


Civil engineering

  • Overall planning incl. application planning, drainage and outdoor facilities planning
  • Trenches and drainage
  • Pipe trenches
  • Installation of pumping stations/separator systems
  • Earthworks
  • Soil stabilisation
  • Soil compaction and creation of load-bearing surfaces for subsequent use
  • Spreading, incorporating, levelling, compacting soil
  • Soil stabilisation consolidation
  • Construction of excavation pits
  • Drainage
  • Laying utility media
  • Asphalt roadways
  • Paved areas
  • Green areas
  • Fire service bypasses
  • Fence and gate systems
  • Industrial road construction
  • Compaction control

DURATION

  • Start: September 2019
  • End: December 2021

 

MACHINE USE

  • Kettenbagger
  • Raupen
  • Radlader
  • Mobilbagger

PLOT SIZE

  • 50.000 m2

An area of 50,000 square metres is being worked on in record time in Wunstorf. The construction site on Adolf-Oesterheld-Straße in the conveniently located industrial estate is seven football pitches in size. From the building application to the completion of the site, including roadways, green areas, fencing and gates, Hagedorn takes care of everything itself. The future tenant was quickly found in the form of an online retailer, allowing Hagedorn to take individual wishes into account, such as preparatory measures for e-mobility.