WHAT WAS DONE
Demolition and pollutant clean-up
- Authority management
- Implementation concept
- Remediation concept
- Environmental/occupational safety concept
- Selective demolition
- Complete demolition
- Demolition of existing buildings
- Urban buildings
- High-rise buildings (over 22 m)
- Foundations
- Demolition in the city centre
DURATION
- Start: September 2020
- End: March 2021
MACHINE USE
- CAT Kettenbagger 330
- Liebherr Longfront R960
CONVERTED SPACE
- 45.000 m3
Our demolition team dismantled a former dermatological clinic including ward block and lecture theatre on the grounds of Kiel University Hospital with kid gloves, so to speak. Due to the close proximity to a cardiology department and drug filling centre, it was important to work as vibration-free as possible. We succeeded: the measuring devices did not malfunction once. We implemented a special traffic concept for the hard-to-reach buildings on the edge of the hospital site. Safety was also a priority during the demolition of the 28 metre high, asbestos-contaminated building. This meant working in the black zone on all six floors.